
Submitted by Gary Ward, General Manager & C.O.O.
Project Update
The next two weeks will be an extraordinarily busy period for bunker work, with multiple crews in numerous locations.
Northgate Farms – Hole-by-hole bunker revitalization,
- #7 – start bunker excavation
- #10 – complete excavation, bunker drainage installation later this week or early next week
- #13 – complete drainage and gravel, spray the Better Billy Bunker (BBB) polymer and install sand and sod at the end of this week
- #15 – Complete sand installation this week, sod installation at the end of this week
- #16 – started bunker drainage and will install gravel at the end of the week in preparation for BBB next week
- #17 – install irrigation this week and sod installation on Friday.
The bunkers on #13, 15, and #17 are planned to be completed by the end of this week.
Over the rest of September in into October they will move to bunker work on #4, #3, #2, #8 and #9. At each stage the other crews will follow the excavation team, and they plan to complete the project and off site by the middle of November.
Whatever holes Northgate Farms are working on will either be closed, or play will be from temporary tees or to a temporary green.
Atkinson Irrigation – Hole-by-hole sprinkler installation,
- #17 - will be completed this week.
- #16 – is planned for next week and should be completed before the end of the week.
- #15 – will be started as soon as #16 is completed.
- #14 – is planned for the last week of the month
In October they hope to complete #13 and then move to the front nine, starting on #7, #5, #4. November will depend on the weather and temperatures, they will either continue with hole-by-hole work or if it’s too cold they will finish mainline installation on #3, #8, #2, #9 and #1. Any unfinished holes, the driving range and entrance road will be completed in 2026.
Whatever hole Atkinson are working on will be closed until completed.
I will continue to keep you informed through a couple videos each week and various other communications including the Project Information Board and in the Mad Post. I will also keep you informed of our performance against the budget.
Please continue to monitor the Project Information Board for the most up-to-date information.